Ventilation ducts are laid on the roof
RIEL Real Estate Corporation reports that the works on the construction site is actively pursued. According to the project manager Vasyl Cherniukhm, the ventilation ducts are laid on the roof these days.
Meanwhile, it is reported that the installation of internal risers of the heating and water supply system come to an end.
According to the builders, the windows have been installed at the facility up to the 24th floor inclusive, preparations for the facade arrangement are underway.
It is also reported that the builders have reinforced the parking wall and are starting waterproofing and backfilling.